Maintenance project wraps up

Author picture
Home / Grazing / Maintenance project wraps up

Monitoring and maintenance of 25 gullies helped ratify lessons learnt around repair

This month the Gully Maintenance and Monitoring project will wrap up.

Between 2017 and 2020, the Burdekin Major Integrated Project (Landholders Driving Change) completed 25 gully remediation projects (five large-scale and 20 small-scale sites).

These gully works treated more than 11,000 linear metres of gullies across 54 gully heads, preventing an estimated 10,500 tonnes of fine sediment from reaching the Great Barrier Reef each year.

Treatments ranged from minor, landholder-led interventions to large-scale engineered solutions using heavy earthworks.

The Queensland Government, through the Queensland Reef Water Quality Program, provided more than $500,000 (including underspend from the initial works) to support long-term monitoring and maintenance.

From June 2022 to April 2025, monitoring and maintenance activities were undertaken across three wet seasons as part of the Burdekin Major Integrated Project Gully Maintenance and Monitoring project.

The project responded to the need for better understanding of cost-effective gully remediation, focusing on how long treatments last, the level and frequency of maintenance required, and whether sediment reductions were sustained.

Its aims were to monitor gully stability, undertake critical maintenance to support confidence in investment outcomes, and generate practical insights into long-term maintenance timeframes and costs.

We would like to thank the graziers and landholders who have supported the Landholders Driving Change and Gully Monitoring and Maintenance projects over many years. Their willingness to provide ongoing access to gully sites for monitoring, along with their commitment to maintaining repaired sites through activities such as weed control and minor in-kind repairs, has been invaluable in building our understanding of gully rehabilitation, monitoring, and long-term maintenance.

Mt Wickham grazier Warren Woodhouse has participated in the maintenance and monitoring of works on his property.
Mt Wickham Station grazier Warren Woodhouse.
Jason Carter, Alluvium Consulting.
NQ Dry Tropics Sustainable Agriculture Program Manager Ron Hunt is flanked by ….

This project is funded by permission of the Queensland Government, through the Queensland Reef Water Quality Program combining an underspend with additional funding.

Read the technical report

Watch the video

Check out the case studies

Four case studies (below ) capture the stories of landholders addressing gully erosion to restore country. They highlight what’s worked, as well as the challenges faced along the way, and the practical lessons learnt.

You might also find these interesting

Please share this project...

Back to Project

Maintenance project wraps up
This month the Gully Maintenance and Monitoring project will wrap up. Between 2017 and 2020, the...

Other stories

Filtering posts by tag pGMM22

Newly completed works rain-tested

A streambank rehabilitation project we’re excited to share in an upcoming video has certainly been on quite the journey. Delivered in the wake of the ...
Read More →

Soil science graduates

We’re thrilled to be part of the Queensland Soil Science Graduate and First Nations Engagement Program, a 12-month initiative accelerating the development of graduate scientists ...
Read More →

Technical report available

For many years, NQ Dry Tropics has been carrying out gully remediation works — large and small — across the Burdekin region. It’s become clear ...
Read More →

Maintenance essential to rehabilitation

Five rock chutes were constructed as part of phase two of the Mt Wickham gully remediation project. The chutes were designed to intercept flows and ...
Read More →

Repair on Belmore gullies working well

The gullies, which have been reshaped, rock chutes installed, and revegetated, were until repair, sending an estimated 4617 tonnes of sediment downstream every year. Until ...
Read More →

Monitoring, maintenance essential for a lasting effect

Since 2022, annual monitoring of 19 remediated small-scale and five large-scale gully sites within the Bowen Bogie Broken (BBB) catchment has been carried out, prioritising maintenance ...
Read More →